This contract was one of the most complicated projects implemented by Sar Albraa Comany due to many challenges we needed to take into consideration.

First, the site work was a high security as we worked in BIAP near the take off and landing lanes.

Second, the difficulties related to escorted laborers, machines and even logistics supplies into the military airport part of BIAP.

Third, working with UNAMI which considered the most high demand organizations related to work standards, health safety and environmental health requirements beside the completion of works within the specified durations of contract.

The company completed the works which including site mobilization, removing old soil, excavation of land and extend pipes for storm water network, build two soak pits, 45 manholes for water collection and pavement of old roads and establishment of new roads and finally pavement of car parks and demobilization of work.

Client: UNAMI

Value: 183,690.00$

Duration: 70 days

Start of works: 24\10\2021

Completion of works: 5\2\2022

Contact information: osman48@un.org Amr Osman kozah@un.org Farouk Kozah

BIAP SAR ALBRAA IRAQ BAGHDAD 2

Light rehabilitation of sanitation network in Jirf Almilh Quarter Baquba Diyala gov.

Related Works

No comment yet, add your voice below!


Add a Comment

Your email address will not be published. Required fields are marked *